Fluor Daniel broke all industry standards by completing its contract for
Texaco Refining and Marketing Inc. (TRMI) in record time. Texaco's
3,444-square-foot "Ring of Fire" StarMart facility, situated on a
one-acre site in Norco, California, includes five pump islands, a
convenience store and two quick-service restaurants, complete with area
paving, site lighting and landscaping, and it was built in just 26 days.
The schedule for a project of this size is typically 100 to 120 days.
Fluor Daniel's Commercial & Infrastructure operating company performed
project management services, which included project planning,
scheduling, preconstruction coordination, construction management and
project close-out activities.
"We originally set a schedule to ensure the project's completion in 39
days and worked two eight-hour shifts each day, 7 days a week. On the
twelfth day of construction, we realized some activities were completing
early, and, with the good cooperation of city officials, we accelerated
our completion date to be just 26 days--an aggressive goal," said Dan
Huff, Fluor Daniel project co-manager.
Grading began on April 1, with the commencement of construction on April
7. Continued Huff, "Our clock started running upon certification of the
building pad and issuance of the building permit." A key development and
technology-first for Fluor Daniel was to pour the foundation grade
beams, set the structural steel framework, frame all exterior walls and
decorative architectural detail, and rough-in and top-out the plumbing
and electrical work, prior to placing the concrete building slab on the
ninth day. Critical inspections were completed, and the project was
accepted by the City of Norco, with a certificate of occupancy being
issued on May 2--the 26th day of construction.
"The task was to construct the project as fast as possible, while being
prudent about cost," said Fluor Daniel Project Co-manager Tom
Sovulewski. "It was evident from the beginning that everyone, including
the City of Norco, was committed to the project and put in extra effort
to break the original 39-day schedule."
TRMI, headquartered in Universal City, California, is a wholly owned
subsidiary of Texaco Inc., which refines, transports and markets
petroleum products in 24 midwestern and western states. Fluor Daniel
Inc., the principal subsidiary of Fluor Corporation, is a global
engineering, construction, maintenance and diversified services company
with more than 60 offices worldwide.