For the construction crews rebuilding a portion of the Kaiser Aluminum
plant in Gramercy, Louisiana, the heat has been on all summer. The
intensity of a fast-track, 24/7 schedule has been augmented by the
extremely hot temperatures.
In the face of it all, the Fluor Daniel project management team has
attained a record of 500,000 safe workhours without an Occupational
Safety & Health Administration (OSHA) recordable injury. Fluor Daniel is
the engineering, procurement and construction unit of Fluor Corporation
(NYSE: FLR).
"A project like this has to run on tight timetables with clockwork
precision," said Win Moore, Fluor Daniel's vice president and project
manager. "Our team was able to accomplish this feat while performing
very precise and detailed coordination of operations on a daily basis.
The Gramercy Rebuild milestone was achieved over a 13-week period
beginning on May 22, 2000.
"Fluor Daniel's outstanding safety record was a key reason it was chosen
for the project," added David Kjos, Kaiser Aluminum vice president and
project director. "We're especially gratified by this latest
achievement."
With 1999 revenues of $12.4 billion, Fluor Corporation provides services
on a global basis in the fields of engineering, procurement,
construction, maintenance, operations, and coal production. Fluor is
headquartered in Aliso Viejo, California.
Keith Karpe or Lori Serrato, Media Relations, Fluor Corporation, (949) 349-3971; or W. Scott Lamb, VP Public Relations, Kaiser Aluminum, (713) 267-3826