Fluor Corporation (NYSE: FLR) announced today that it has been chosen to
complete the Luna Energy Facility located near Deming, New Mexico.
Contract value to Fluor was not disclosed and was booked in the first
quarter.
Tucson Electric Power Company, Phelps Dodge Energy Services, LLC, and a
development subsidiary of PNM Resources (NYSE: PNM) have chosen Fluor to
finish work at the 570-megawatt, combined cycle power plant, which was
50 percent complete when construction was stopped by the original owner
in 2002. Under terms of the contract, Fluor will provide engineering,
procurement, construction and commissioning.
"We are extremely pleased to be chosen for completion of the Luna Energy
Facility," said Bob Mickey, senior vice president of Power, a unit
within Fluor's Energy & Chemicals group. "The expertise and capabilities
of Fluor's employees are a perfect fit for this work. This award will
allow us to effectively support our client's objectives for the Luna
Energy Facility."
Construction began this month, and employees in Fluor's Houston office
are working to complete the project by summer 2006.
Fluor Corporation (NYSE: FLR) provides services on a global basis in the
fields of engineering, procurement, construction, operations,
maintenance and project management. Headquartered in Aliso Viejo,
Calif., Fluor is a FORTUNE 500 company with revenues of $9.4 billion in
2004. For more information, visit www.fluor.com.
Jerry Holloway/Leann VandergriftMedia Relations949.349.7411/7420Lila ChurneyInvestor Relations949.349.3909 tel949.349.5375 fax